Auburndale Commissioners Say the City Got Lucky On A Data Center Without Enforceable Decibel Limits
Note from the Editor: The City of Auburndale workshop from Nov. 10 can be viewed on our Facebook page. Don't forget to hit that follow button.
Auburndale city officials told the standing-room-only crowd at Hamann Hall at Lake Ariana Park that the city’s code has no decibel limits for the data center planned at Pace Road in Auburndale and that, because of SB180, they cannot adopt one before Oct. 1, 2027. They confirmed they follow state guidelines for noise limits, which regulate only motor vehicle noise, not commercial noise.
Commissioners told residents at the workshop there will be no future vote on the project. Two city commissioners said Tuesday evening that the protections residents do have come from the developer’s own choices, not the city’s rules.
Vice Mayor Jordan Helms, who said he owns an engineering firm and has spent 20 years in heavy industry, told the room he is neither for nor against the data center. He brought up Senate Bill 180, which came out of the 2025 legislative session, was backdated to Aug. 1, 2024, and runs until Oct. 1, 2027. “During this time here, we’re unable to change [our] development regulations,” he said. “We can’t make them more restrictive.” Then, “We are physically handcuffed by the state.”
“I think we were lucky, not good,” Helms said. “And what I mean by that is we were exposed. We were kind of lucky that Hillwood came in with a good design.” He closed by saying the city has to do better. “You got to be able to demand good developments in our area,” he said. “And I don’t think we’re there right now.”
Commissioner Crystal Tijerina said a few minutes later, the city “got lucky because it could have been a lot worse.”
Governor Ron DeSantis signed SB 484, or the data center law, in May at Florida Polytechnic University. The bill is meant to protect residents from carrying the cost burden and also created a new section of state water law providing that a permit application from a large-scale data center may not be approved without a hearing. The city did not say whether the Southwest Florida Water Management District (SWFWMD) would require its own hearing, since Preble said the city currently has the capacity to provide the water the developer says the data center needs.
The developer’s own engineering undercut residents’ concerns. Salas O’Brien, the firm that sealed the plans, told the commission the cooling system is fully air-cooled with “no active water” used, and put evaporative alternatives at millions of gallons a day. A Hillwood executive confirmed that the facility’s projected 4,665 gallons per day is entirely for domestic use, not cooling. Records presented Tuesday show the site’s former agricultural water use permit allowed an average of 212,700 gallons a day, with a maximum of nearly 3.5 million.
The engineer conceded the trade from water to noise. Air-cooled chillers, he said, “naturally produce some noise.” The company commissioned an acoustical firm, recorded existing sound at multiple points across a full weekend before anything is operating, and modeled the result at the property boundary. His conclusion was that post-mitigation levels will land at or slightly below the recorded baseline at every offsite point once acoustic walls at the chillers and a perimeter sound barrier are installed. Hillwood put property line noise at a level “consistent with a quiet conversation.” The room laughed.
None of that, however, is enforceable. Preble told the commission the city’s noise ordinance has no decibel limit, then said a section of the land development regulations covers noise and that the state regulates it.
The section she cited, 5.3.3.4, is a table of maximum permitted vibration displacement in inches. The performance standards it belongs to cover vibration, air pollution, radiation, odors, toxic matter, fire, humidity, glare, electromagnetic interference, outdoor storage, and liquid disposal. It doesn’t say anything about noise.
Florida doesn’t have a uniform statewide noise code either, and noise regulation is primarily local. Auburndale adopted its own overlay article for the Central Florida Innovation District in 2024. Section 15.607 of that article prohibits the following: “No activity shall be conducted that produces noise, odors, dust, fumes, fire hazard, or other nuisance beyond the property lines.” It does not set a decibel limit for the noise it prohibits.
The same section prohibits buildings over 200,000 square feet. The permit application lists the building at 268,810 square feet. In March 2024, staff told the Planning Commission that any future renovation would be subject to the district standards, and the city has not said whether they apply here. Murphy, the city attorney, told the commission the director’s presentation was thorough and her explanations accurate.
Commissioner Sean Levy, who said he downloaded a decibel meter and took his own readings while coaching soccer at Lake Myrtle, pressed for conditions instead. He asked for binding developer agreements, city-monitored meters to verify the water figure, mandated acoustic shielding, and proactive measurement at both high and low frequency. “We cannot rewrite what was passed in 2023,” he said, “but under Florida law, we have full authority to enforce our codes today.” He drew the loudest applause of the night.
The permit application describes more than an interior retrofit. Its scope of work covers interior tenant development within the existing building shell, including interior and exterior mechanical and electrical infrastructure, as well as site civil alterations for mechanical and electrical infrastructure, including relocation of parking spaces. Asked whether two backup generators covered full capacity “once all 4 buildings are up and running,” the development team said the application filed Nov. 4 represents the first phase and that later buildout would add one generator per building. Every figure presented Tuesday, for water, sound, power and tax revenue, describes only the first phase.
Regarding the power, the statute defines a large-scale data center as a single location drawing an anticipated monthly peak load of 50 megawatts or more. The mechanical plans for 810 Pace Road label four suites inside Building 1 that total 120 megawatts.
Tampa Electric laid out a power build that had not been reported previously. Two looped 230-kilovolt transmission lines will run to the site, fully paid for by the developer. The data center will construct and use its own substation, and the utility will build a switchyard beside it.
Carlos Aldazabal, Tampa Electric’s vice president of energy supply, said large loads require a system impact study that the developer funds, that it takes months, and that the developer pays for all resulting transmission upgrades. Tampa Electric also told the commission the existing Pace Road substation, which runs at distribution voltage and serves customers including SunTrax, is not intended to serve the data center, and that recent upgrades and transformer work there were done primarily for 20 megawatts of battery storage already in the utility’s 10-year site plan.
More than 60 residents filed speaker cards. Colby Todd, who lives on Carla Ann Court, argued the Nov. 4 permit, labeled a commercial interior renovation, amounts to a major modification of the binding site plan and should return to the planning commission.
Sheryl Manche of Winter Haven asked whether the developer would commit to a C-weighted decibel standard rather than the A-weighted measure that discounts low-frequency sound.
William Wysinger pointed to the new state statute and said property line readings do not predict what residents hear inside their homes. Clyde Glace asked what happens if the developer does not deliver, and whether the remedy is a fine the company simply pays.
Theresa Detwiler, of Auburndale, answered the city attorney’s property rights argument directly, saying,
“We all have rights,” she said, “including the next door neighbors.”
Theresa Detwiler, Auburndale resident
Desiree’ Vaughn of Polk City asked what consequences Hillwood faces if permanent job creation comes in at half what the company projects, and whether any financial penalty attaches to missing those numbers.
Among those who spoke during public comment were state Rep. Octavio Hernandez (D), who won the Florida House District 51 seat Nov. 3; Alethea Pugh (D), who ran for Florida House District 48; and Atheena Wilson, Victor Sims’ school board campaign manager. Polk County Commissioner Becky Troutman attended the meeting, but did not speak.
Murphy identified a narrower lever. Asked about the utility’s pending rate filing, he said that if the tariff and the energy issues are not resolved, “that would be a basis on which to deny the approval of a permit,” while cautioning that much of the project’s future “depends on things that are outside the control of this commission.” Tampa Electric filed its large load customer tariff with the Florida Public Service Commission on Sept. 30. It remains in discovery, with a hearing the utility’s representative believes is set for March 30.
The zoning that made the project possible passed Dec. 18, 2023, nearly two years before Commissioners Travis Avery, Sean Levy and Crystal Tijerina took office. Ordinance 1761 moved the future land use from Polk County Interchange Activity Center-X to City of Auburndale Regional Activity Center, and Ordinance 1762 set Industrial Planned Unit Development zoning, both on 75.89 acres. Both passed on all ayes, with Helms among the commissioners voting. The city’s planning commission had recommended denial 3-2 that October over the buildings’ size and truck traffic from a logistics use. The developer revised the plan, and the ordinance that followed attached one list of permitted uses to the two buildings on the west side of the property and a different list to the buildings on the east.
Twelve miles away, Lakeland took the opposite path in August; after public opposition over Project Swan, a 600,000-square-foot data center project, its commission adopted a one-year moratorium on new data centers and any business expected to draw 50 megawatts or more, 4-3. Lakeland’s city attorney said data centers are not a listed allowed use in that city’s development code, so staff already treats them as prohibited, and he called the moratorium a belt-and-suspenders measure.
Auburndale’s position is the reverse. Its staff reads a data center into the research and development use its 2023 ordinance permits, a definition that names communications and information technology among its industries but does not name data centers or data storage.
That difference, not the state law, is why one city can act and the other says it can’t. SB180 does bar Auburndale from adopting a moratorium or any more restrictive land development regulation before Oct. 1, 2027.
Keeping Polk County informed is exactly why we’re here. Follow The Citrus Tea News for more local coverage, or subscribe to The Citrus Tea News e-Weekly at the link in our bio.

Truly Local news. Truly Polk County.
Your community. Your news. Your right to know. Follow The Citrus Tea News for real local news across Polk County, and subscribe to our free e-Weekly newsletter at the links below. We welcome your comments and questions. Send us a message to reach our team.
Frequently Asked Questions
Is the Auburndale data center approved?
No. The city received a site plan and permit application Nov. 4, 2026, and it remains under staff review. At Tuesday’s workshop, the mayor said no action would be taken and no vote held, and two commissioners said again the project will not return to the commission for a vote.
How much water will the Auburndale data center use?
Hillwood projects 4,665 gallons a day, which a company executive said is entirely domestic use. The engineering firm that sealed the plans said the cooling system uses no water. The property’s potable water permit allows up to 42,975 gallons a day, and the site’s former agricultural permit allowed an average of 212,700.
How much power will the Auburndale data center use?
The mechanical plans label four suites in Building 1 totaling 120 megawatts, and describe those loads as initial estimates to be finalized when a tenant fits out the space. Two looped 230-kilovolt transmission lines will serve the site, paid for by the developer. The development team said the Nov. 4 application covers the first phase only.
Will the Auburndale data center be loud?
Auburndale’s code sets no decibel limit, and Florida has no statewide noise standard. The developer’s acoustical modeling projects levels at or slightly below existing recorded sound at offsite points once acoustic walls and a perimeter barrier are built, but nothing in the city’s regulations requires that result.
Can the public still speak about the Auburndale data center?
Yes, at City Commission meetings, which include a public comment period not limited to agenda items. State law enacted in 2026 also requires a hearing before a water permit application from a large-scale data center can be approved, but that applies only if the data center files its own application rather than buying water from the city.
Sources: “Auburndale Data Center Plans Show 120 Megawatts As Residents Get First Chance to Speak at City Workshop,” The Citrus Tea News, thecitrustea.com, Nov. 10, 2026; “How Auburndale Approved a Data Center Without Saying It Out Loud,” The Citrus Tea News, thecitrustea.com, Nov. 6, 2026; “Lakeland Commission Passes Data Center Moratorium In 4-3 Vote,” The Citrus Tea News, thecitrustea.com, Aug. 3, 2026; Special City Commission Workshop, City of Auburndale, Nov. 10, 2026; Public Comment Registration Cards, Special City Commission Workshop, City of Auburndale, obtained through public records request, Nov. 10, 2026; Commercial Building Permit Application, Building 1, 810 Pace Road, City of Auburndale, obtained through public records request, Nov. 6, 2026; Ordinance 1762, Exhibit B, City of Auburndale, obtained through public records request, 2023; City Commission Minutes, City of Auburndale, Dec. 18, 2023; Planning Commission Minutes, City of Auburndale, March 5, 2024; Project Sunshine mechanical plan set, 810 Pace Road, Salas O’Brien, obtained through public records request, Sept. 21, 2026; Land Development Regulations, Chapter 5, Article 3, City of Auburndale, auburndalefl.com, undated; Land Development Regulations, Chapter 15, Article 5, City of Auburndale, auburndalefl.com, updated April 2026; Chapter 2026-65, Laws of Florida, Florida Legislature, May 7, 2026; Chapter 2025-190, Laws of Florida, Section 28, Florida Legislature, 2025; Petition for Approval of Large Load Customer Tariffs by Tampa Electric Company, Florida Public Service Commission, floridapsc.com, Sept. 30, 2026; Ordinance 26-018, City of Lakeland, Aug. 3, 2026; Record LDNON-2026-53, Polk County Land Development Division, polkfl.gov, July 6, 2026; “Lakeland Approves One-Year Moratorium on Data Centers,” LkldNow, lkldnow.com, Aug. 3, 2026; Cherie Jacobs, media spokesperson, Tampa Electric, written statements, Sept. 24 and Nov. 6, 2026, City of Auburndale Commission Minutes, Dec. 1, 2025, page 138, first agenda item, “INSTALL COMMISSIONERS ELECT-TRAVIS AVERY, SEAN LEVY, AND CRYSTAL TIJERINA.”