Auburndale Will Draft A Data Center Moratorium That They Say SB180 Voids
Auburndale is considering a pause on new data centers. If the commission adopts a moratorium, it will not apply to the Project Sunshine on Pace Road in Auburndale. City officials have said SB180 would void any adopted moratorium as soon as it passes.
City Manager Jeffrey Brown announced the plan for a moratorium on Monday night, during announcements at the regular commission meeting. He tied it to the Nov. 10 workshop and to conversations with commissioners. Staff met with the city attorney earlier that day. A first reading would come at the second December meeting, with a second reading at the first meeting in January.
Brown also said staff has begun looking for an outside consultant to review every study the developer has submitted. The city already employs consultants for site plan review. This one would be brought in to check Hillwood’s work on the Pace Road project.
The pause would not stop the Pace Road Data Center from moving forward. The property is zoned to permit the project, and the city has reiterated that the 2023 approvals allow the project to continue without going back to the commission for a vote. The city is looking at a one-year pause to add more restrictions and guidelines for future data centers.
SB180 applies to every city in any county named in the Hurricane Debby, Helene, or Milton disaster declarations, which includes all of Polk. The state law bars a moratorium on construction, reconstruction, or redevelopment of property damaged by those storms. A separate clause doesn’t have a damage qualifier. It bars “more restrictive or burdensome amendments” to a comprehensive plan or land development regulations. It also bars more burdensome procedures for reviewing a site plan or development permit. Anything adopted in violation is “null and void ab initio.” The law backdated to Aug. 1, 2024, and runs until Oct. 1, 2027, Vice Mayor Jordan Helms said at the Nov. 10 working, “Assuming we don’t have another hurricane that gives it another extension.”
The city has already faced challenges regarding adding restrictions. The Department of Commerce wrote to the city on Sept. 22, 2025, finding its proposed comprehensive plan amendments void under Section 28. The city withdrew the ordinance, spent two months stripping provisions out alongside its consultant and attorney, and adopted a revised plan in April. Commerce never identified which sections were the problem; however, Julie Preble, Auburndale’s Community Development Director, told The Citrus Tea News it wasn’t related to the data center.
Helms told the Nov. 10 workshop that the same law left the commission powerless. “We are physically handcuffed by the state,” he said, adding that Auburndale could not make its development regulations more restrictive before the law expires.
Helms did not answer the roll at either meeting and cast no votes. Partway through the agenda, Brown noted for the record that Helms was listening on a Teams call. The approvals behind the project predate most of the people now weighing a moratorium. Ordinances 1761 and 1762 changed the future land use designation on 75.89 acres north of Pace Road and rezoned the property for an industrial planned unit development. Both cleared first reading unanimously on Nov. 20, 2023, and both needed four of five votes because the Planning Commission had recommended denial, 3-2. None of the five commissioners who cast those votes still serve.
Project Sunshine’s project on Pace Road will continue to move forward. Hillwood’s application to retrofit the interior of one building reached the city on Nov. 4, and permitting and outside agency reviews are set for early next year.
Keeping Polk County informed is exactly why we’re here. Follow The Citrus Tea News for more local coverage, or subscribe to The Citrus Tea News e-Weekly at the link in our bio.

Truly Local news. Truly Polk County.
Your community. Your news. Your right to know. Follow The Citrus Tea News for real local news across Polk County, and subscribe to our free e-Weekly newsletter at the links below. We welcome your comments and questions. Send us a message to reach our team.
Frequently Asked Questions
Is Auburndale banning data centers?
No. Staff is drafting a moratorium that would pause new applications. Nothing has been written, read, or voted on. A first reading is expected at the second commission meeting in December, with a second reading at the first meeting in January.
Will the moratorium stop the data center on Pace Road?
No. The property already carries zoning that allows the project, and the city has said the 2023 approvals govern it. Hillwood’s retrofit application reached the city Nov. 4 and remains under review.
Can a Florida city adopt a data center moratorium right now?
It is contested. Section 28 of Chapter 2025-190, Laws of Florida, applies to cities in the Hurricane Debby, Helene and Milton disaster counties. Until Oct. 1, 2027, it bars a moratorium on storm-damaged property. It also bars making land development regulations more restrictive or burdensome. Anything adopted in violation is void from the start.
Has another Polk County city passed a data center moratorium?
Yes. Lakeland adopted a 12-month moratorium on a 4-3 vote in August under Ordinance 26-018. It covers customers of Lakeland’s utilities inside and outside the city limits and sets no megawatt threshold.
Who is the developer behind the Auburndale data center?
Hillwood Development Company, through an entity named Pace Road DC Development LLC. The company’s internal name for the project was Project Sunshine, and the city announced it as the Auburndale Technology Center.
Sources: “Auburndale Commissioners Say the City Got Lucky On A Data Center Without Enforceable Decibel Limits,” The Citrus Tea News, thecitrustea.com, Nov. 16, 2026; “City Commission and Community Redevelopment Agency meeting audio recording,” City of Auburndale, obtained through public records request, Nov. 16, 2026; “Planning Commission Meeting agenda packet,” City of Auburndale, auburndalefl.com, Jan. 6, 2026; Chapter 2025-190, Section 28, Laws of Florida, flsenate.gov, 2025; “Ordinance 26-018,” City of Lakeland, lakelandgov.net, Aug. 3, 2026; “Building permit application BC-26-0177, 810 Pace Road,” City of Auburndale, obtained through public records request, Nov. 4, 2026; “City Commission,” City of Auburndale, auburndalefl.com, undated; “Auburndale to consider data center pause, but controversial project can move forward,” Tampa Bay 28, tampabay28.com, Nov. 16, 2026